Building Our School
This page shows the photographic progress of how our new school was built.
Newest images at the top
************

September 2018-Start of our Forest School.

November 2017-New playground equipment for Reception.

July 2017-Window screening added.


31st October 2016-We are open for learning.




31st October-The classes are ready.


13th October-Almost there!

15th September-Inside the building flooring going down and units fitted.

10th September-The outside of the building is almost complete.

25th July-Wooden cladding going on.

25th July-Main hall air vents installed and trunking going in for electricals.

25th July 2016-Up on the roof!

22nd April 2016-Southern elevation – VCL installation onto Metsec walling underway as well as cladding trims, topsoil spread in preparation for seeding, final levelling of pathways, Southern playground and feature mounding underway.

22nd April 2016-Main roof looking down on gym and first floor partitioning of rooms.
 
 
22nd April 2016-Southern elevation looking north west and ground floor rooms/ corridor starting to be defined.
 
  
2nd April 2016-Stairs in and ground floor partition framework commenced, M&E containment complete and pipework underway.
************

29th March 2016-Top floor in and halls started.

29th March 2016-Roof started and kitchen area being erected.
************

3rd February 2016-Ground Breaking Ceremony.
 
  
3rd February 2016-Ground Breaking Ceremony and site visit.

3rd February 2016-Site visit with School Council and poster winners.
************
 
 
25th January 2016-The first floor is now under way.
 
 
25th January 2016-Building continues.
************
 
 
21st December 2015-Looking East to West – Slab reinforcement
and phase 1 concrete pour to ground floor slab.
 
 
21st December 2015-Looking West to East – Rebar in progress following DPM and insulation
and deep drainage to the rear of the gym.
********

2015 November 24th-Groundworks well underway.
 
 
2015 November 24th-The work continues in the rain.
********

2015 October 26th-Onsite visit.
 
 
2015 October 26th-Foundations started.
********

2015 October 9th-Main Entrance.
 
 
2015 October 9th-Preparing the ground.
********

2015 September 25th-The main entrance in to the school.
 
  
2015 September 25th-Preparing the land where the main building will be.
*********