Our New School

This page shows the photographic progress of how our new school was built.

Newest images at the top

 

************

 

31st October 2016-We are open for learning.

 

 

31st October-The classes are ready.

 

 

13th October-Almost there!

 

 

15th September-Inside the building flooring going down and units fitted.

 

 

10th September-The outside of the building is almost complete.

 

 

25th July-Wooden cladding going on.

 

 

25th July-Main hall air vents installed and trunking going in for electricals.

 

 

25th July 2016-Up on the roof!

 

 

22nd April 2016-Southern elevation – VCL installation onto Metsec walling underway as well as cladding trims, topsoil spread in preparation for seeding, final levelling of pathways, Southern playground and feature mounding underway.

 

 

22nd April 2016-Main roof looking down on gym and first floor partitioning of rooms.

 

 

 

22nd April 2016-Southern elevation looking north west and ground floor rooms/ corridor starting to be defined.

 

  

 

2nd April 2016-Stairs in and ground floor partition framework commenced, M&E containment complete and pipework underway.

 

************

 

 

29th March 2016-Top floor in and halls started.

 

 

29th March 2016-Roof started and kitchen area being erected.

 

************

 

3rd February 2016-Ground Breaking Ceremony.

 

  

 

3rd February 2016-Ground Breaking Ceremony and site visit.

 

 

3rd February 2016-Site visit with School Council and poster winners.

 

************

 

 

 

25th January 2016-The first floor is now under way.

 

 

 

25th January 2016-Building continues.

 

************

 

 

 

21st December 2015-Looking East to West – Slab reinforcement

and phase 1 concrete pour to ground floor slab.

 

 

 

21st December 2015-Looking West to East – Rebar in progress following DPM and insulation

and deep drainage to the rear of the gym.

 

********

 

 

2015 November 24th-Groundworks well underway.

 

 

 

2015 November 24th-The work continues in the rain.

 

********

 

 

2015 October 26th-Onsite visit.

 

 

 

2015 October 26th-Foundations started.

 

********

 

 

2015 October 9th-Main Entrance.

 

 

 

2015 October 9th-Preparing the ground.

 

********

 

 

2015 September 25th-The main entrance in to the school.

 

  

 

2015 September 25th-Preparing the land where the main building will be.

 

*********