Home Page

Building Our School

This page shows the photographic progress of how our new school was built.

Newest images at the top




31st October 2016-We are open for learning.



31st October-The classes are ready.



13th October-Almost there!



15th September-Inside the building flooring going down and units fitted.



10th September-The outside of the building is almost complete.



25th July-Wooden cladding going on.



25th July-Main hall air vents installed and trunking going in for electricals.



25th July 2016-Up on the roof!



22nd April 2016-Southern elevation – VCL installation onto Metsec walling underway as well as cladding trims, topsoil spread in preparation for seeding, final levelling of pathways, Southern playground and feature mounding underway.



22nd April 2016-Main roof looking down on gym and first floor partitioning of rooms.




22nd April 2016-Southern elevation looking north west and ground floor rooms/ corridor starting to be defined.




2nd April 2016-Stairs in and ground floor partition framework commenced, M&E containment complete and pipework underway.





29th March 2016-Top floor in and halls started.



29th March 2016-Roof started and kitchen area being erected.




3rd February 2016-Ground Breaking Ceremony.




3rd February 2016-Ground Breaking Ceremony and site visit.



3rd February 2016-Site visit with School Council and poster winners.






25th January 2016-The first floor is now under way.




25th January 2016-Building continues.






21st December 2015-Looking East to West – Slab reinforcement

and phase 1 concrete pour to ground floor slab.




21st December 2015-Looking West to East – Rebar in progress following DPM and insulation

and deep drainage to the rear of the gym.





2015 November 24th-Groundworks well underway.




2015 November 24th-The work continues in the rain.





2015 October 26th-Onsite visit.




2015 October 26th-Foundations started.





2015 October 9th-Main Entrance.




2015 October 9th-Preparing the ground.





2015 September 25th-The main entrance in to the school.




2015 September 25th-Preparing the land where the main building will be.